地鐵報告附件12
3.10 At 31 March 2013, the reported actual delay to Contract 810A was 341 days. An entitlement to 259 days Extension of Time has since been acknowledged by the Corporation for the period up to 31 March 2013. This included an entitlement to an Extension of Time against Completion Obligations in the north top-down area of 291 days.
其意思是,在去年3月尾,地鐵公司已同意(has since been)承建商禮頓-金門聯營在西九龍總站(北)延遲259日(『追回措施』之前)。可以推斷,路政署在去年3月已知道這一嚴重延誤。